Thankfully the rain only delayed the pouring of the slab by four days. I was very surprised as the ground was sodden and I wasn't sure they'd get their machinery onto the block. John the builder put more gravel down to help the tradies access the block.
Five days after the slab was poured, much of the frame has been erected.
Wednesday, June 29, 2016
Wednesday, June 22, 2016
Slowly, slowly.......
Not much has happened since the last post. The rain has delayed things for a week. The weekend saw torrential rain, after a week of showers.
The slab will be poured on Friday 24 June. Plumbing and so forth is being done beforehand. A couple of photos to catch up.
The slab will be poured on Friday 24 June. Plumbing and so forth is being done beforehand. A couple of photos to catch up.
After the rain
At least there's a loo now.
Preparing for the foundation